AC:实际成本,actual costACWP:已完工作实际成本,Actual Cost for Work PerformedBAC:完工预算,budget at completionCCB:变更控制委员会,change control boardCOQ:质量成本,cost of qualityCPAF:成本加奖励费用合同,cost plus award fee contractsCPFF:成本加固定费用合同,cost plus fixed fee contractCPI:成本绩效指数,cost performance indexCPIF:成本加激励费用合同,cost plus incentive fee contractCPM:关键路径法,critical path activityCV:成本偏差,cost varianceEAC:完工估算,estimate at completionEF:最早完成日期,early finish dateEMV:预期货币价值,expected monetary valueES:最早开始日期,early start dateETC:完工尚需估算,estimate to completeEV:挣值,earned valueEVM:挣值管理,earned value managementFF:完成到完成,Finish-to-FinishFFP:固定总价合同,Firm-Fixed-Price ContractFMEA:失效模式与影响分析,Failure Mode and Effect AnalysisFP-EPA:总价加经济价格调整合同,Fixed Price with Economic Price Adjustment ContractsFPIF:总价加激励费用合同,Fixed Price Incentive Fee ContractFS:完成到开始,Finish-to-StartIFB:投标邀请书,Invitation for BidLF:最晚完成日期,Late Finish DateLOE:支持型活动,Level of EffortLS:最晚开始日期,Late Start DateOBS:组织分解结构,Organizational Breakdown StructurePDM:紧前关系绘图法,Precedence Diagramming MethodPMBOK:项目管理知识体系,Project Management Body of KnowledgePV:计划价值,Planned ValueQFD:质量功能展开,Quality Function DeploymentRACI:执行、负责、咨询和知情矩阵,Responsible、Accountable、Consult、Inform MatirxRAM:责任分配矩阵,Responsibility Assignment MatrixRBS:风险分解结构,Risk Breakdown StructureRFI:信息邀请书,Request for InformationRFP:建议邀请书,Request for ProposalRFQ:报价邀请书,Request for QuotationSF:开始到完成,Start-to-FinishSOW:工作说明书,Statement of WorkSPI:进度绩效指数,Schedule Performance IndexSS:开始到开始,Start-to-StartSV:进度偏差,Schedule VarianceSWOT:优势、劣势、机会与威胁,Strengths,Weaknesses,Opportunities,ThreatsT&M:工料,Time and MaterialWBS:工作分解结构,Work Breakdown Structure
I小蘑菇I
引论专区 投资回收期:PBP:Pay Back Period 投资回报率:ROI:Return On Investment 净现值:NPV:Net Present Value 内部收益率:IRR:Internal Rate Return 成本效益分析:CBA:Cost Benefit Analysis 范围专区 质量功能展开:QFD:Quality Function Deployment 联合应用设计或开发:JAD:Joint Application design and Development 进度专区 关键路径法:CPM:Critical Path Method 最早完成日期:EF 最早开始日期:ES 紧前关系绘图法:PDM:Precedence Diagramming Method 进度绩效指数:SPI:Schedule Performance Index 成本专区 AC(ACWP):Actual Cost || Actual Cost Work Performed PV(BCWS):Plan Volue || Buget Cost Work Scheduled EV(BCWP):Earn Vlue || Buget Cost Work Performed 成本绩效指数:CPI:Cost Performance Index 成本偏差:CV:Cost Variance 完工估算:EAC:Estimate at Completion 完工尚需估算:ETC:Estimate To Completion 挣值:EV:Earned Value 挣值管理:EVM:Earned Value Managment 质量专区 质量成本COQ:Cost Of Quality 资源专区 组织分解结构:OBS:Organizational Breakdown Structure 责任分配矩阵:RAM:Responsibility Assignment Matrix 经典责任分配矩阵(负责、执行、咨询、知情):RACI :Accountable、Responsible、Consult、Inform 风险专区 优势、劣势、机会与威胁:SWOT:Strength Weakness Opportunity Threat 采购专区: 投标邀请书:IFB:Invitation For Bid(等同于建议邀请书) 信息邀请书:RFI:Request For Information 报价邀请书:RFQ:Request For Quotation 建议邀请书:RFP:Request For Proposal 工作说明书:SOW:Statement Of Work 工作大纲:TOR DBB模式:Design Bid Build 总承包模式(交钥匙):EPC:Engineering Procurement Construction 特许运营:BOT:Build Operation Transfer 自己运营:BT:Build Transfer 固定总价合同:FFP:Firm Fixed Price 总价加激励费:FPIF:Fixed Price Plus Incentive Fee 总价加经济价格调整:FP-EPA:Fixed Price-Economic Price Adjustment 成本加固定费:CPFF:Cost Plus Fixed Fee 成本加激励费:CPIF:Cost Plus Incentive Fee 成本加奖励费:CPAF:Cost Plus Award Fee 工料合同T&M 需要记的单词 Actual:实际的 Completion:完工、完成 Budget:预算 Board:委员会 Quality:质量 Cost:成本 Economic:经济 Adjustment:调整 Incentive:激励 Fee:费用 Fixed:总体的、总共的 Benefit :效益 Analysis:分析 Performance:绩效 Index:指数 Critical:关键的 Variance:方差、偏差 Estimate:估算、估计 Organizational:组织 Breakdown:分解 Structure:结构 Diagramming:图表 Deployment:部署、展开 Matrix:矩阵 Responsibility:责任 Consult:咨询 Inform:知情、通知 Statement:说明、表述 Schedule :进度 Strength:优势 Weakness:劣势 Opportunity:机会 Threat:威胁 Duration:持续 BaseLine:基准 Iteration:迭代 Optimistic 乐观 Pessimistic 悲观 May 最可能,可能
evanzheng2013
进度绩效指数就是SPI(Schedule Performance Index)
首先得介绍几个概念:
Earn Value(赚值:完成时机工作的预算价值)
Planned Value(计划值: 计划在规定时间之前在活动上花费的成本的总价值,记预计投入)
Actual Value(实际成本)
SPI=EV/PV,如果SPI大于1表示进度提前,反之表示落后。
赢得值法的四个评价指标在这三个基本参数的基础上,可以确定赢得值法的四个评价指标,它们也都是时间的函数。
1.费用偏差CV(Cost Variance)
费用偏差(CV)=已完工作预算费用(BCWP)-已完工作实际费用(ACWP) (10—43)
当费用偏差CV为负值时,即表示项目运行超出预算费用;当费用偏差CV为正值时,表示项目运行节支,实际费用没有超出预算费用。
2.进度偏差SV(Schedule Variance)
进度偏差(SV)=已完工作预算费用(BCWP)-计划工作预算费用(BCWS) (10—44)
当进度偏差SV为负值时,表示进度延误,即实际进度落后于计划进度;当进度偏差SV为正值时,表示进度提前,即实际进度快于计划进度。
3.费用绩效指数(CPl)
费用绩效指数(CPI)=已完工作预算费用(BCWP)/已完工作实际费用(ACWP) (10-45)
当费用绩效指数(CPl) <1时,表示超支,即实际费用高于预算费用;
当费用绩效指数(CPI) >1时,表示节支,即实际费用低于预算费用。
4.进度缋效指数(SPl)
进度绩效指数(SPI)=已完工作预算费用(BCWP)/计划工作预算费用(BCWS) (10-46)当进度绩效指数(SPI) <1时,表示进度延误,即实际进度比计划进度拖后;
当进度绩效指数(SPI) >1时,表示进度提前,即实际进度比计划进度快。
费用(进度)偏差反映的是绝对偏差,结果很直观,有助于费用管理人员了解项目费用出现偏差的绝对数额,并依此采取一定措施,制定或调整费用支出计划和资金筹措计划。但是,绝对偏差有其不容忽视的局限性。如同样是10万元的费用偏差,对于总费用1000万元的项目和总费用1亿元的项目而言,其严重性显然是不同的。
因此,费用(进度)偏差仅适合于对同一项目作偏差分析。费用(进度)绩效指数反映的是相对偏差,它不受项目层次的限制,也不受项目实施时间的限制,因而在同一项目和不同项目比较中均可采用。
进度绩效指数SPI
进度绩效指数SPI(Schedule Performance Index,SPI)是测量进度绩效的一种指标,表示为挣值与计划价值之比。反映了项目团队利用时间的效率。
SPI=挣值(EV)/计划价值(PV),当SPI>1时,表示进度提前,即实际进度比计划进度快;当SPI<1时,表示进度延误,即实际进度比计划进度慢。
费用绩效指数(CPI)
费用绩效指数 Cost Performance Index (CPI)项目管理中成本管理领域中的名词,是项目费用效率的一种度量。计算方法为费用绩效指数=已完成工作预算费用/已完成工作实际费用。即: CPI =BCWP/ACWP。